Whatsapp Resmi Dewa16 SLOT THAILAND https://dewa16.co.uk/ https://bola16.co.uk/ slo16 slot gacor http://siad.dpmd.gorutkab.go.id/ https://journal.binadarma.ac.id/pages/article/deposit-pulsa-tanpa-potongan/ https://stennisflagflyers.com/ https://nanotechinstitute.org/ slot gacor https://hollyvalance.net/ slot gacor deposit pulsa tanpa potongan slot thailand deposit pulsa tanpa potongan slot gacor hari ini slot pulsa slot pulsa https://dewa16.id/ slot gacor slot16 BOLA16 BOLA16 SLOT16 slot gacor deposit pulsa tanpa potongan https://sertifikasi.upy.ac.id/assets/mgacor/ http://103.141.105.92/ slot gacor slot gacor slot gacor slot dana slot gacor slot gacor slot thailand slot pulsa slot kamboja slot gacor https://sibangkodir.bpsdm.jatimprov.go.id/api/gacor deposit pulsa tanpa potongan slot kamboja https://littlebeedesigns.co.uk/ slot gacor maxwinhttps://siakad.stikeslakipadada.ac.id/sgacor/ https://stikeslakipadada.ac.id/gacor slot gacor slot dana deposit pulsa tanpa potongan slot thailand slot pulsa https://ppsdml.bpsdm.dephub.go.id/rames/toto/ https://kejari-sanggau.kejaksaan.go.id/ramestoto/ http://conference.fkm.unand.ac.id/rames/toto/ slot thailand togel online slot gacor slot gacor deposit pulsa tanpa potongan deposit pulsa tanpa potongan slot thailand slot gacor slot thailand deposit pulsa tanpa potongan

PERHITUNGAN WAKTU STANDAR DALAM PERAWATAN KENDARAAN DENGAN METODE WORK SAMPLING

  • Eko Basiron Kurniawan Universitas Bina Darma
  • Christofora Desi Kusmindari Universitas Bina Darma
Keywords: work sampling, Standard Time, Hour Measurement

Abstract

Work sampling is an activity of measuring work for standard time, the proportion for
lost time (idle/delay) and seeing the proportion of non-productive activities that take
place in a certain time cycle. Periodic maintenance has the highest percentage of units,
including external periodic service (SBEK). From the results of the initial analysis,
the type of vehicle that performs periodic maintenance is dominated by the Avanza
with a total of 654 units. In this vehicle process, the vehicle takes 180 minutes which
is far more than the standard time target of 60 minutes. The method used in this study
is the work sampling method which measures the workload of employees through
productive and non-productive performance in order to find out what the standard
output of work in Toyota Avanza maintenance is. The results of this study are (1) in
the process of maintaining Toyota vehicles on the Avanza unit, the standard time
obtained is: 40.2 minutes. (2) the number of workers needed by the company in
carrying out Toyota vehicle maintenance is: 28,17 or 28 people. (3) the calculation of
the workload of technicians' productivity in completing the toyota avanza vehicle
maintenance work is 108%.