Whatsapp Resmi Dewa16 SLOT THAILAND https://dewa16.co.uk/ https://bola16.co.uk/ slo16 slot gacor http://siad.dpmd.gorutkab.go.id/ https://journal.binadarma.ac.id/pages/article/deposit-pulsa-tanpa-potongan/ https://stennisflagflyers.com/ https://nanotechinstitute.org/ slot gacor https://hollyvalance.net/ slot gacor deposit pulsa tanpa potongan slot thailand deposit pulsa tanpa potongan slot gacor hari ini slot pulsa slot pulsa https://dewa16.id/ slot gacor slot16 BOLA16 BOLA16 SLOT16 slot gacor deposit pulsa tanpa potongan https://sertifikasi.upy.ac.id/assets/mgacor/ http://103.141.105.92/ slot gacor slot gacor slot gacor slot dana slot gacor slot gacor slot thailand slot pulsa slot kamboja slot gacor https://sibangkodir.bpsdm.jatimprov.go.id/api/gacor deposit pulsa tanpa potongan slot kamboja https://littlebeedesigns.co.uk/ slot gacor maxwinhttps://siakad.stikeslakipadada.ac.id/sgacor/ https://stikeslakipadada.ac.id/gacor slot gacor slot dana deposit pulsa tanpa potongan slot thailand slot pulsa https://ppsdml.bpsdm.dephub.go.id/rames/toto/ https://kejari-sanggau.kejaksaan.go.id/ramestoto/ http://conference.fkm.unand.ac.id/rames/toto/ slot thailand togel online slot gacor slot gacor deposit pulsa tanpa potongan deposit pulsa tanpa potongan slot thailand slot gacor slot thailand deposit pulsa tanpa potongan

INTERVAL WAKTU PERAWATAN KOMPRESSOR AMMONIA PADA PEMBUATAN CARBON DIOKSIDA LIQUID MENGGUNAKAN MONTE CARLO (Studi kasus di PT.Pupuk Sriwidjaja Palembang)

  • Dionysius Ardian Indra Setyawan Universitas Bina Darma
  • Ch Desi Kusmindari Universitas Bina Darma
Keywords: Breakdown maintenance, preventive maintenance, simulation, Monte Carlo

Abstract

PT. PUPUK SRIWIDJAJA PALEMBANG (PUSRI) is a petrochemical industry that is engaged in fertilizer production, especially urea. The production activities can take place well if the engine performance is perfect . Ammonia compressor has the most failure frequency compared to other machines . Long duration of the ammonia compressor breakdown reached 21% of the total repair. The intensity of failure can be prevented with effective preventative maintenance. Determination of treatment time intervals can be determined by several methods. A method that is often used is the Monte Carlo simulation. The result of the research and critical components of the compressor with treatment time are carried out every three months with repair cost of Rp 76.487.514

PT. Pupuk Sriwidjaja Palembang (PT. PUSRI) merupakan industri petrokimia yang bergerak dalam produksi pupuk khususnya, pupuk urea. kegiatan produksi belangsung dengan lancar apabila performa mesin sempurna .Kompressor ammonia memiliki frekuensi kegagalan terbanyak dibandingkan dengan mesin lainnya. Lama waktu breakdown kompressor ammonia mencapai 21% dari total keseluruhan perbaikan. Intensitas kegagalan dapat dicegah dengan perawatan pencegahan yang efektif. Penentuan interval waktu perawatan dapat ditentukan dengan beberapa metode. Salah satu metode yang sering digunakan adalah simulasi Monte Carlo. Hasil penelitian dari komponen kritis kompressor dengan waktu perawatan yang dilakukan setiap tiga bulan sekali dengan biaya perbaikan sebesar Rp 76.487.